Current Projects

List of Proposed Projects to be Built in 2018

CWATS is developing bikeways and pathways throughout Essex County.  Once complete, a total of 793 km of facilities will be built in our region. 

Location

Road Name

Facility

From

To

Length (km)

Essex CR 50 Paved Shoulders 455 CR 50 597 CR 50 1.2

Kingsville

CR 50

Paved Shoulders

CR 23

90m south of Sycamore Ave.

4.1

Kingsville

CR 20

Paved Shoulders

Greenway

Dimenna Drive

3.6

Kingsville

CR 20

One-Way Cycle Track

Dimenna

CR 45

0.5

Lakeshore

CR 2

Paved Shoulders & Multi Use Trail    (3.1km each)

Rail Corridor North  ROW Limit

Patillo Road

3.1

Leamington

CR 20 

One-Way Cycle Track

CR 31

600m east of CR 31

0.6

Leamington

CR 20

One-Way Cycle Track

 1.2km east of CR 31

60m west of Sherk St. 

2.1

County of Essex

Various County Roads

Design Projects

   

5.3

 Map of Projects Planned for 2018

2018 CWATS Projects-Status

2018 CWATS projects are just being tendered.Paved shoulders on CR 50 in Essex and Kingsville Tender close June 15, 2018

Final section of the Kingsville One-Way Cycle Path is being constructed and should be completed by the end of July!.

The One-Way Cycle Path from Kingsville (CR 31) to Leamington (Sherk) will be tendered in June with award anticipated in July, 2018

The paved shoulder program is off to a great start with CR 2 (CR 2 to CR 22), CR 11 (CR 18 (pike) to CR 18) and CR 15 (S. Malden to CR 18) awarded. June -October 2018.

Multi-use Trail will be constructed on both sides of CR 22 from CR 25 to I.C. Roy by October 2018.

The remaining projects are currently in the design phase.